May 29, 2017

AMC BOS™ recovers an abandoned hole and boosts productivity in Arizona, USA

MC BOS™ was a success at the Resolution Mine, saving a borehole that had been abandoned, reducing the costs and improving the productivity of the hole.
May 29, 2017
In all my time drilling at this site, I have never witnessed a product do what the AMC BOS™ had done to improve drilling and loss circulation conditions.
Eric Castleberry, the Drill Supervisor from Resolution Copper trial comments on using the AMC BOS™ for lost circulation
May 29, 2017

AMC BOS™ saves 77% in operational costs compared to traditional cementing method

AMC BOS™ reduced drilling fluids needed by 50%, eliminated the need for a costly, time consuming cementing/grouting and improved the average bit life used.
January 31, 2017
AMC BORE HOLE STABILISER

AMC BORE HOLE STABILISER improved blast hole utilisation by 30%.

AMC’s BORE HOLE STABILISER performed exceptionally well compared to the existing program and resulted in an increased hole utilisation rate of 30% and produced significantly more holes per hour.
January 30, 2017
We can now drill more meters with AMC BORE HOLE STABILISER as no PVC is needed to case the holes
The Production Engineer for our Kalgoorlie trial comments on using AMC’s BORE HOLE STABILISER instead of the traditional PVC method.
January 4, 2017
AMC’s SRU on the DM Civil site.

AMC’s SRU facilitated the early completion of a civil construction project.

AMC’s SRU facilitated the early completion of the micro tunnelling project, reducing the project by four to seven days, while a further five days saving was gained by eliminating the need to dispose of up to 137,500L of fluid.
October 4, 2016
SRU onsite in North West Territories, Canada

77% reduction in water use achieved by AMC’s HP SRU in the Arctic tundra

AMC’s Heli-portable SRU reduced the risk of environmental contamination, reducing water consumption and increasing efficiencies in Canada.

Case Studies

May 29, 2017

AMC BOS™ recovers an abandoned hole and boosts productivity in Arizona, USA

MC BOS™ was a success at the Resolution Mine, saving a borehole that had been abandoned, reducing the costs and improving the productivity of the hole.
May 29, 2017

AMC BOS™ saves 77% in operational costs compared to traditional cementing method

AMC BOS™ reduced drilling fluids needed by 50%, eliminated the need for a costly, time consuming cementing/grouting and improved the average bit life used.
January 31, 2017
AMC BORE HOLE STABILISER

AMC BORE HOLE STABILISER improved blast hole utilisation by 30%.

AMC’s BORE HOLE STABILISER performed exceptionally well compared to the existing program and resulted in an increased hole utilisation rate of 30% and produced significantly more holes per hour.
January 4, 2017
AMC’s SRU on the DM Civil site.

AMC’s SRU facilitated the early completion of a civil construction project.

AMC’s SRU facilitated the early completion of the micro tunnelling project, reducing the project by four to seven days, while a further five days saving was gained by eliminating the need to dispose of up to 137,500L of fluid.
October 4, 2016
SRU onsite in North West Territories, Canada

77% reduction in water use achieved by AMC’s HP SRU in the Arctic tundra

AMC’s Heli-portable SRU reduced the risk of environmental contamination, reducing water consumption and increasing efficiencies in Canada.
September 12, 2016
AMC BORE HOLE STABILISER at the Mungari Gold Mine Site, Kalgoorlie

AMC BORE HOLE STABILISER reduced total drilling costs by 34% in Western Australia

AMC BORE HOLE STABILISER successfully negated the need for traditional PVC casing at an underground mine in the Goldfields region of Western Australia.